mPix Risk Items: No Duration



What it is: 
The amount of time allowed to complete a task has not been provided one or more instances. The duration is the number of days given for the task to be completed. This is different from the work estimate, which is the amount of active work time that will be needed to complete the task at hand. For example, you are given Monday and Tuesday to write a proposal and you expect that it will take three hours to write. The duration is two days (Monday and Tuesday) and the work estimate is three hours. 

Why it matters: On a micro level, it lets your team members know how many days they'll have to get their work done. On a macro level, only when a duration has been assigned for every task can you determine the total number of days needed to complete your project. The duration combined with dependencies (the order that tasks should be performed in) allows Moovila to calculate and provide a truly accurate forecast for your project's completion.
Before durations have been added--note that the number of days associated with the Critical Path is currently five. This assumes that each SmartTask will take one day to complete.
2020-10-01_11-24-51.png
After durations have been added--note the number of days listed at the end of the Critical Path now accurately captures time required to complete this project.
2020-10-01_11-27-44.png

 

What's next: Add a duration for every task in your project plan. This is easiest to do quickly in Power Grid or Timeline view mode. By default, all durations are set to one day. If you're not sure how much time is needed, check with the team members responsible for completing those SmartTasks, or use a duration with some padding.
2020-10-01_11-26-23.png

Once all dates have been entered and saved, go to the Critical Path view for the project and click Update Timeline.
2020-10-01_11-27-24.png