The following rules apply when Moovila is determining the hourly cost to apply to a user:
1. See if a user has an hourly cost…if no…
2. See if the time entry has a resource type (and get hourly cost) …if no…
3. See if the user has a resource type(and get hourly cost) …if no…
4. See if the task has a resource type(and get hourly cost) …if no…
5. Get the enterprise default for hourly cost