Working a Project: Editing Dependencies in Power Grid View

 

  1. Open a project. Select the Power Grid view from the main navigation.
    2023-03-22_09-58-54.png

  2. Click on the Dependencies icon in the upper right corner of the application. 
    2023-03-22_09-58-54.png

  3. The Edit Dependencies screen appears. Click into the Predecessors column for the desired SmartTask, and edit.
    2023-03-22_09-59-17.pngMultiple tasks may be entered as predecessors or successors by adding a comma between line numbers.

    The following dependency types are available by entering the short code alongside the task's line number. 
    • Start-to-Start: SS (e.g. a start-to-start dependency on a task in row 87 would be entered as 87SS)
    • Finish-to-Finish: FF (e.g. a finish-to-finish dependency on a task in row 87 would be entered as 87FF)
    • Lag: +x"unit of time" where time units are abbreviated as "y" "m" "w" "d" (e.g. a lag of 3 days on a task in row 87 would be entered as 87+3d)
    • Lead: -x"unit of time" where time units are abbreviated as "y" "m" "w" "d" (e.g. a lead of 3 months on a task in row 87 would be entered as 87-3m)
  4. Upon returning to the Edit Dependencies screen, you may click Save to save all changes made, or Cancel to discard changes.
    2023-03-22_09-59-38.png

  5. If changes have been made to dependencies, you will be prompted to update dates on SmartTasks impacted by the changes. 
    2023-03-22_09-59-54.png
    a.  Click YES to update SmartTasks with the proposed dates or NO to leave dates as they were previously.
    b. Click ON, to send out a date change notification, if desired.
  6. Click Save.
Was this article helpful?
1 out of 1 found this helpful

Comments

0 comments

Article is closed for comments.